Reviewing each project to accelerate the public investment capital disbursement

Comrade Dao My, the PPC Vice Chairman, has recently chaired a working session with the Management Board of Investment and Construction Projects in the provincial eastern region combined with its affiliated management boards to assess the situation of public investment capital disbursement as well as discuss measures to overcome difficulties and accelerate the project implementation progress.

In 2026, the Management Board of Investment and Construction Projects in the Eastern region is assigned to manage over 3,418.8 billion VND in public investment capital, including approximately 1,847 billion VND of planned capital for 2026 along with nearly 1,572 billion VND carried forward from 2025.

As of July 3rd, the unit had disbursed over 1,059 billion VND (30.99% of the plan). Concurrently, the Tuy An Investment and Construction Project Management Board has disbursed over 163 billion VND (28.03% of the plan); the Tuy Hoa Investment and Construction Project Management Board is striving to achieve a cumulative disbursement rate of 38.88% by July.

 

The PPC Vice Chairman, comrade Dao My, addressing the working session.
The PPC Vice Chairman, comrade Dao My, addressing the working session.

During the meeting, the units stated that compensation alongside land clearance continue to be the most problematic bottleneck to the progress of public investment capital disbursement. Numerous projects remain delayed due to land disputes, inheritance documents, complex land use origins, public complaints, together with the technical infrastructure relocation.

Some projects, although restarted, can only proceed slowly because the land handed over is not yet complete. The procedures for licensing earth mines serving public investment projects remain cumbersome combined with time-consuming, affecting construction progress and disbursement.

To improve disbursement performance, project management boards stated they would coordinate with localities to accelerate compensation and land clearance work. Simultaneously, they would review the progress of each project to promptly resolve any arising obstacles, striving to complete the registered disbursement plan in July coupled with subsequent months.

Concluding the meeting, the Provincial Party Committee member and PPC Vice Chairman, comrade  Dao My requested that investors, localities, as well as relevant departments and agencies focus intensely on disbursing public investment capital; reviewing each project coupled with each item, clearly identifying difficulties, obstacles, together with the responsibilities of each unit to determinedly  resolve them. Matters falling within their authority must be addressed immediately; while issues beyond their jurisdiction should be promptly reported to the PPC for consideration and direction.

The PPC Vice Chairman requested localities alongside units to accelerate land clearance work, shorten the processing time for related procedures, especially the licensing of material mines. At the same time, it’s also to strengthen coordination among the project management boards, localities, and departments as agencies by clearly defining responsibilities, developing specific implementation plans for each part of the work, while resolutely achieving the target of disbursing public investment capital on a weekly and monthly basis.

Translated by TRINH THUY

Your Opinion