Stepping up disbursement of project funds in November

The PPC has organised an inspection team to review progress alongside urge faster implementation of key transport projects invested in by the Provincial Management Board of Transport and Agriculture and Rural Development Construction Investment Projects.

PPC Chairman, comrade Do Huu Huy directing relevant units to accelerate construction and disbursement for the Ea Ho - Tam Giang Road Project.
PPC Chairman, comrade Do Huu Huy directing relevant units to accelerate construction and disbursement for the Ea Ho - Tam Giang Road Project.

The team inspected construction progress on the road project linking Ea Ho and Tam Giang in the former Krong Nang District, as well as the project to renovate and upgrade Provincial Road 13, from Km6+840 to Km25+00.

At the construction sites, PPC Chairman, comrade Do Huu Huy stressed that disbursement of public investment capital, particularly funds carried forward from 2025 into 2026, must not be delayed. Project owners must therefore require contractors to commit to specific schedules and regularly monitor as well as urge implementation of approved disbursement plans. PPC Chairman called on relevant units to concentrate resources on construction and disburse funds corresponding to completed work in November 2026, rather than allowing workloads to accumulate towards year-end.

PPC Chairman, comrade Do Huu Huy affirmed that the province was continuing to step up public investment to drive socio-eco growth. The province would review and select capable, reputable combined with responsible contractors in pursuit of its common development goals. Contractors that fail to meet commitments or demonstrate poor performance would be excluded from subsequent bidding packages.

*Earlier, PPC Chairman Do Huu Huy also inspected the project to invest in and operate infrastructure at Phu Xuan Industrial Park (IP).

Phu Xuan IP construction began on April 24, 2026. To date, the investor has completed the construction packages for the regulating lake, temporary fencing and 750 kV transformer station, while work on the remaining packages is underway.

PPC Chairman, comrade Do Huu Huy working with the project investor and representatives of provincial departments alongside agencies.
PPC Chairman, comrade Do Huu Huy working with the project investor and representatives of provincial departments alongside agencies.

Following an on-site inspection, Do Huu Huy asked the investor to honour its construction schedule commitments and accelerate progress, particularly on items involving ground levelling, asphalt paving, the transformer station, greenery along with landscaping.

Provincial leaders directed the investor to require contractors to mobilise maximum resources and expedite construction to ensure planned output. The province will inspect alongside urge progress on projects funded by non-state budget sources with the same rigour applied to public investment projects. The Dak Lak Economic Zones and IPs Management Board was tasked with monitoring while updating data on construction progress reported by investors and contractors. It was also asked to accelerate appraisal together with approval of investment policies for projects seeking to invest in IPs, thereby contributing to the provincial growth in the coming period.

Translated by HAI LOAN 