Dak Lak Province has reduced capital plans of 44 projects to increase funding for 15 others, reallocating a total of more than 309.3 billion VND. The aim is to unblock public investment capital and make it a solid lever for the goal of double-digit GRDP growth.
Identifying the bottlenecks correctly
The province has a very large volume of development investment capital, placing considerable pressure on disbursement as the year-end peak approaches. Alternate Member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee and PPC Chairman, comrade Do Huu Huy, has frankly pointed out the bottlenecks in disbursement. With a target of disbursing more than 90% of its overall capital plan, the province has asked the Department of Finance to draw up specific scenarios and feasible solutions, while directing units to disburse capital resolutely.
![]() |
| PPC Vice Chairman, comrade Dao My, inspecting projects at Hoa Phu Industrial Park. |
In practice, disbursement at many project management boards remains below expectations. The Provincial Management Board for Investment and Construction of Transport and Agricultural and Rural Development Works (Board A) has committed to disbursing only 78.12% of its 2026 capital allocation by December 31. In addition, more than 300 billion VND of carried-over 2025 capital remains undisbursed.
The Provincial Management Board for Investment and Construction of Civil and Industrial Works (Board B) has disbursed 89% of its carried-over 2025 capital alongside nearly 67% of its 2026 capital. The delay is due to substantial additional funding concentrated on four inter-level boarding schools, which were allocated 365 billion VND of central government capital in August coupled with October, equal to 50% of the 2026 capital plan. Besides this, three of Board B's projects are still waiting for the province to issue a decision adjusting land price coefficients so that compensation prices for site clearance can be applied.
At commune and ward level, several units received their capital allocations on October 22 but had still not disbursed any of it after 20 days. The 210 billion VND allocated for science along with technology can barely be used and cannot be reallocated due to incomplete procedures. Some units have asked to halt projects, while three large-scale education projects have yet to be approved.
Firm capital reallocation
The Provincial Party Committee, the Provincial People's Council and the PPC have issued a series of directives alongside action plans guided throughout by the principle of "clear personnel, clear tasks, clear responsibilities, clear timelines and clear results". PPC Chairman, comrade Do Huu Huy, criticised project management boards for hesitating while holding on to capital, waiting until they could "increase advances" or "complete site clearance" before disbursing. The provincial leadership has directed that capital be reallocated early and decisively so that other projects can absorb it.
![]() |
| Contractors speeding up construction of the section of the Khanh Hoa - Buon Ma Thuot Expressway running through Dak Lak Province. |
PPC Vice Chairman, comrade Truong Cong Thai, called for the acceptance and payment for contractors to be settled once and for all. He also asked the Department of Finance and the Department of Construction to shorten appraisal timelines for adjustments to total investment, labour, machinery combined with contract duration, preventing delays in disbursement through the State Treasury. Regarding capital advances, the province is applying an advance rate of 40%, which falls under the authority of the Department of Finance. If the target of disbursing more than 90% remains unmet, an advance rate of 50-60% will be submitted to the PPC Chairman for approval.
The Department of Finance has also been tasked with reviewing revenue from land use fees and land auctions in central wards, estimated at nearly 3 trillion VND, in preparation for a report to the Provincial People's Council.
With coordinated, resolute alongside flexible action from provincial to grassroots level, Dak Lak is building new momentum to turn public investment capital into a solid lever for achieving its double-digit growth target.